| Clean Global Energy |
Board Director & Technical Partnership Agreement |
July 2008 onwards (Director since October 2009) |
Overgas Inc. AD, Sofia, Bulgaria
|
Technical Advisor and Consultant on UCG and UCG-CCS |
September 08 onwards
|
| White Coal Energy, Hungary |
Technical Consultant |
December 2008 onwards |
| Sunflag Oil and Gas |
Partner in Bidding Process for UCG Blocks in India |
November 2008 onwards
|
| Newcastle University |
NE Offshore Study |
Mar 2008-Dec 2008 |
Heriot-Watt and Scottish & Southern Energy Plc
|
Phase 2 of the study to gasificy coal under the Firth of Forth, Scotland
|
May 2007
|
European Commission
|
Sub-Contractor for €3.1M Project HUGE (Hydrogen Underground Gasification Europe)
|
December 2007
|
Major East European Gas Company
|
Development of proposals for a UCG trial
|
July 2007
|
Sindh Coal field Interests, Pakistan
|
Formulation and initial investigation of a large UCG project for gas to liquids
|
January 2006 to August 2007 (project currently in suspension)
|
Neveli Lignite Company, India
|
Joint submission for a UCG trial in S India
|
Mar 2006 –present
|
UK Department of Trade and Industry, London, UK
|
Technical Advisor on UCG Technical
|
2004 – 2006 |
Supervisor for Phase 1 of Feasibility Study of UCG under the Firth of Forth, Scotland
|
to Dec 2005
|
Contract studies on advanced drilling, environmental and regulatory issues of UCG, UK coal resources for new technologies, public perception of UCG, site reviews of UCG
|
to December 2005
|
Technology Status Report of Directional Drilling in Coal
|
March 2004 – Jan 2005
|
BP plc, UK
|
World wide review of UCG
|
June 2005 – October 2005
|
Energy Edge Ltd, UK
|
Partners in BP review
|
June 2005 – October 2005
|
Universe Oil and Gas, Nevada, USA
|
Preparatory work for a deep UCG trial in NE China
|
Sept 2004 – August 2005
|
Liaohe Oil Bureau, (Subsidiary of Petrochina National Oil Company, China
|
Preliminary feasibility study for designing and operating of a deep UCG Trial
|
August 2005 to March 06
|
Energy Technology Partners, LLC, Pittsburgh, PA, USA
|
Pre-feasibility UCG study for confidential client in Wyoming
|
March 2005 – June 06
|
UK Department of Trade and Industry, London, UK (as independent consultant)
|
Technical Advisor on UCG Technical Supervisor for
|
Jan 2001 – August 2004 |
The Coal Authority, UK (as independent consultant)
|
Identification and preparation of trial UCG site at Silverdale Colliery, Shropshire, UK,
|
Sept 1999 – October 2001
|
Underground gasification Europe, (UGE) AEIE, Spain
|
Director for European Field Trial of UCG
|
Dec 1996- June 1999
|